
Oracle sends force majeure notice on its New Mexico Stargate data center
The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
以下正文同步自 TechCrunch,版权归原站所有,已转换为易读排版。
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.
Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online.
The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for customers like OpenAI.
Oracle maintains that it does not expect a delay. “Project Jupiter remains on our planned schedule,” Oracle said in a statement to CNBC. “We are fully committed to New Mexico and confident in our path forward.”
Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that “this notice does not change the financial commitments to this multi-year project.”
Neither Oracle nor Blue Owl immediately responded to TechCrunch’s requests for comment.
Still, the notice follows a string of setbacks at the site, many of them tied to its energy supply. The campus, designed to handle 2.45 gigawatts, is meant to run on gas-powered fuel cells from Bloom Energy, which makes a reliable gas supply central to its timeline
An Energy Transfer pipeline intended to deliver gas to the site has also been delayed nearly six months, to Feb. 1, 2027, after regulators repeatedly denied permits for the line. In August, Bloomberg reported that the pipeline’s route had been changed following those rejections. A separate air quality permit for the fuel cell system that would power the campus is also pending. The state’s environment department faces a Nov. 23 deadline to decide.
Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term. The campus has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections. Oracle has responded with a public outreach campaign in the state aimed at winning over the project’s critics, according to Bloomberg.
When you purchase through links in our articles, we may earn a small commission. This doesn’t affect our editorial independence.
Aditya Mehta
Editorial Fellow
October 13 – 15
San Francisco
Your next big connection is at Disrupt.
Connect with 10,000+ founders, VCs, operators, and tech leaders. Explore tomorrow’s breakthroughs, hear what’s shaping tech today, and save up to $200 by Sept. 25 at 11:59 p.m. PT.
Anthropic says its biology lab has already found something big
Julie Bort
PitPro’s first tire-changing robot goes live in Canada
Sean O'Kane
Anthropic releases Opus 5.5 with lower prices and Fable-level performance
Russell Brandom
Meta’s Muse is outpacing ChatGPT’s early mobile launch
Sarah Perez
Tilly Norwood’s press tour is going about as well as you’d expect for an AI
Amanda Silberling
Anthropic is operating a lab that conducts biology experiments
Julie Bort
A new kind of AI model from a ChatGPT inventor is thrilling developers
Tim Fernholz
正文由 探How 从来源站点 RSS 同步,内容未经改写;遇到排版缺失或需要图片、视频时请以原文为准。